Ownership: 100 %
Production: 30 GWh
Power: 9 MW

Løkaunet hydropower plant is located on the Nidelva river in Klæbu Municipality in Sør-Trøndelag County. The power plant utilises a gross head of 51 metres from Hyttsaga. The water level in lake Bjørsjøen is regulated between 158 and 152 metres above sea level. Lake Bjørsjøen is continuous with lake Selbusjøen when the reservoir is full.

The power plant consists of one Francis turbine with an installed capacity is 9 MW. The power plant started production in 1926. The Svean and Bratsberg power plants utilises the water in Nidelva river from lakes Selbusjøen/Bjørsjøen in parallel with Løkaunet power plant.