Ulset

Ownership: 48.6 %
Production: 140 GWh
Power: 35 MW

Ulset power plant is located in the Orkla watercourse in Tynset Municipality, Hedmark County. The power plant is equipped with a Francis turbine and has an installed capacity of 35 MW.

The annual average production is 140 GWh. The power plant uses a gross height of fall of 325 metres from the intake reservoir Lake Storsverjesjøen. Water is also drawn from the regulating reservoir Lake Falningsjøen and two stream intakes. The power plant was commissioned in 1985.

There is a 500 metre long tailrace tunnel from the plant that leads the water back to the Orkla River.

Ulset is part of Kraftverkene i Orkla (KVO). TrønderEnergi Kraft is the operator of the power plant.