Event ID Power Plant Status Publication Time Event Start Estimated End Installed Capacity (MW) Available Capacity During Event (MW) Cause
124130-12.1 Baillie Planned – Completed 22.02.2021 15.44 19.10.2021 08.00 19.10.2021 16.00 53 53 Maintenance
122990-12.1 Baillie Planned – Superseded 02.02.2021 15.44 19.10.2021 08.00 19.10.2021 16.00 53 0 Maintenance
122990-12.2 Baillie Planned – Completed 02.02.2021 15.24 19.10.2021 08.00 19.10.2021 16.00 53 0 Maintenance